If you're pricing a lot outside Kempner, what will water cost you three years after you move in? Kempner Water Supply Corporation's posted rates answer that for this month. They're less helpful for the years after that. The co-op's board kept rates flat for its 2026-27 budget while staff projected a revenue shortfall of about $334,640. A rate study meant to set the future rate structure is expected to finish in early 2027.
KWSC's planned plant upgrade, a clarifier, is set up to be financed in a new way. Most of the money is expected to come from a wholesale water customer, a planned estate development in Salado. For anyone buying land in KWSC's service area, the price of water and the condition of the water now both depend on that deal.
What you pay before the first gallon
Start with the costs a land buyer runs into first. KWSC's current rates page lists these charges for a standard 3/4-inch meter:
- Membership fee: $300
- Impact fee: $2,550
- Equity buy-in fee: $850
- Tap fee: $1,300
- Meter drop-in fee: $650
The table lists each fee separately and doesn't say which ones combine on a particular new-home application. Ask the office for a written figure for your parcel instead of adding up the table yourself. KWSC also has a separate preliminary application marked for raw land only. It asks for the property location, acreage or abstract, and a plat, survey, field notes or metes-and-bounds description where one applies. The application is valid for 30 days after the office reviews it.
The monthly bill has climbed for two decades
Once you're connected, the monthly base charge for a 5/8 x 3/4-inch meter is $80. Usage costs $7.05 per 1,000 gallons for the first 2,000 gallons and rises through tiers to $8.00 per 1,000 above 30,000 gallons. That base charge is the latest step in a long climb, as KWSC's own rate increase history shows:
| Date | Monthly base rate | Usage rate per 1,000 gallons |
|---|---|---|
| July 2002 | $25, up from $18 | $1.95 as of January 2003 |
| March 2015 | $62.50 | $3.15 |
| October 2019 | $70 | $4.50 |
| October 2022 | $75 | $5.25 |
| October 2023 | $75 | Tiered, starting at $7.05 |
| October 2025 | $80 | Tiered, $7.05 to $8.00 |
The 2025 increase took effect in early October 2025, according to KWSC's rate notice. Connection fees have followed the same path. The impact fee was $1,000 in May 2015, reached $2,000 by September 2023, and is $2,550 on today's rate page.
The co-op's raw water costs are rising too. KWSC draws from Stillhouse Hollow Lake, and it pays the Brazos River Authority for the right to that water. BRA's system water rate was $99.50 per acre-foot in fiscal 2025. On July 27, 2026, BRA's board adopted $113 per acre-foot for fiscal 2027, an increase of about 14 percent over two years. KWSC's August budget discussion named that BRA increase as one of the pressures on the budget.
Why the board held rates anyway
At the August 26, 2026 meeting, directors debated whether to build a rate increase into the new budget. One director warned that keeping current rates "could result in a larger rate increase being necessary in the future." Others pointed to uncertainty in seasonal water sales, revenue from bulk water sales not yet in the budget, and the pending Mustang Springs contract. The board approved the budget 6-1 "without a rate increase at this time" and said it would reassess later in the fiscal year.
Today's rate holds while the board waits for the rate study and the wholesale contract.
The plant runs below its design numbers
The wholesale deal grows out of an old problem. KWSC's September 2025 Q&A addressed member complaints about discolored water directly:
"Ideally, a clarifier would have been installed to pre-treat the water prior to it entering the plant; however, this was not part of the facility's original design due to the historically higher quality of the lake water, and its addition now would entail significant costs beyond current budgetary constraints."
The same answer said several areas of the lake have elevated manganese levels and that KWSC is among the systems affected.
At the March 25, 2026 board meeting, staff explained that the capacity figures in TCEQ's Water Watch reflect the plant's design numbers, "not what the Plant produces due to the lack of a Clarifier." For a growing service area, the clarifier is a capacity question as well as a water quality one.
A Salado development changes the math
Mustang Springs at Salado is planned on 1,105.07 acres north of FM 2843, about 5.4 miles west of I-35. It was annexed into the Village of Salado on May 18, 2023, according to the Salado Village Voice. The paper reported plans for three phases with 599 single-family estate lots in total, plus land set aside for mixed use, commercial use, a public school site and water storage. It also reported houses valued at $1 million or more and an estimated $65 million in improvement costs for the proposed public improvement district.
KWSC's March 2026 minutes describe the deal as a "Wholesale Contract 6 miles from the Plant." At that meeting, a Mustang Springs representative said the development would maintain its own system and install its own tank. He also said it would not be responsible for a clarifier at a cost of $15,000,000. One director objected to the draft and asked how the wholesale rate compared with what members pay.
The deal changed over the next four months. At a May 18 workshop on a proposed 2 MGD allocation, directors raised concerns about the risk of "Mustang Springs or related investors failing financially after infrastructure debt is incurred" and asked for more protections. On July 6, the board approved the long-term wholesale contract 6-1. The approved version made a second 500,000-gallon-per-day capital contribution mandatory within 24 months. It also required that the capital contributions and past BRA reserve funds received under the contract go to the clarifier project unless the board acts otherwise.
On July 22, the minutes recorded that Mustang Springs had not yet signed the contract. The cash-flow plan the board reviewed that night shows how the cost would be split:
| Clarifier funding source | Preliminary figure |
|---|---|
| Kempner WSC's portion | $4.1 million |
| Mustang Springs, initial contribution | $6.3 million |
| Mustang Springs, later contribution | At least $6.3 million |
Under that plan, the Salado development's contributions would cover roughly three dollars for every dollar from KWSC. Even KWSC's own share isn't fully in hand. The board discussed temporarily using reserves, then possibly a line of credit or, if necessary, additional debt. That same night, the board accepted a letter of intent from LAN Engineering Services. By August 26, management expected the contract to be finalized after a meeting with Mustang Springs representatives the next day, with engineering for the connection to start once the agreement was final. Staff also said Mustang Springs plans to size part of its infrastructure for future capacity and that more BRA water rights could be needed as demand grows.
KWSC's own words in 2025 explain the logic: "Additional meters will help distribute costs among a larger membership base." Mustang Springs is that idea at the scale of a wholesale customer, with a large outside buyer expected to help pay for an upgrade the co-op said in 2025 it couldn't afford on its own. KWSC's $4.1 million share, and whatever it costs to finance, still lands on members' rates.
Other projects in the same budget
The clarifier isn't the only project. In July, staff reported that a one-million-gallon storage tank was under construction and a generator project was close to finished. Silt and debris had built up around the raw water intake, and a preliminary dredging estimate of about $160,000 was discussed, possibly shared with WCID No. 1. In August, the City of Lampasas asked for a joint meeting to discuss forming or joining a regional water authority. The board's discussion covered financing, shared facilities, water rights and possible effects on customer rates.
Each of these projects feeds into the rate study.
Questions to ask before you close on land
Bring these to KWSC, either at 512-932-3701 or 254-547-9430, or at a monthly board meeting, where members get an open session to raise questions:
- Which connection fees apply to my parcel, and what's the total in writing?
- Will my lot need a line extension or an engineer's study, and what have infrastructure costs been on similar tracts nearby?
- When does the board expect rate study recommendations, and when would new rates take effect?
- Where does the clarifier project stand, and how is KWSC's share being financed?
- Is my parcel in a part of the system where staff are planning service improvements, such as the possible new injection site for the northern portion of the system mentioned in August?
KWSC's board minutes are posted on its board meetings page, and they're the best place to follow the rate study as it moves toward early 2027. This is general information, not legal or financial advice. Confirm fees, contracts and financing for your own parcel with KWSC and the right professionals.
At Wayfinder Builders, we price water service into every build-on-your-land budget before you buy the lot, including the fees, the line to the property and the rate questions still open. If you're looking at land in the Kempner area, bring us the parcel and we'll work through the water numbers with you before you sign anything.